Pertanyaan 1
Anda adalah supervisor proyek konstruksi. Anda menerima laporan kemajuan proyek berikut:
"Project Status Update: City Bridge Renovation
Date: October 26, 2023
Prepared by: Engineering Team
Progress Summary:
- Foundation work: 90% complete (ahead of schedule)
- Steel structure erection: 60% complete (on schedule)
- Road paving: 10% complete (delayed due to unexpected heavy rain last week)
Upcoming Challenges:
- Procurement of specialized asphalt for road paving.
- Potential labor shortage next month due to holiday season.
Next Steps:
- Expedite asphalt procurement.
- Develop contingency plan for labor shortage."
Berdasarkan laporan tersebut, masalah terbesar yang sedang dihadapi proyek saat ini dan perlu segera diatasi adalah?
- Foundation work: 90% complete (ahead of schedule)
- Steel structure erection: 60% complete (on schedule)
- Road paving: 10% complete (delayed due to unexpected heavy rain last week)
- Procurement of specialized asphalt for road paving.
- Potential labor shortage next month due to holiday season.
- Expedite asphalt procurement.
- Develop contingency plan for labor shortage."